Co-Optimization of Generation and Transmission for Expansion Planning – Part 3

Welcome to part 3/3 of this blog series on co-optimized generation/transmission expansion planning! Part 1 gave an introduction to optimization/linear programming and illustrated the superiority of co-optimized expansion planning over generation-only or transmission-only expansion planning using an example from Krishnan et. al (2015). Part 2 dove deep into the mathematics for three different levels of fidelity for modeling power flows in an expansion planning model: transshipment, DCOPF, and ACOPF, ordered from simplest to most complex.

This blog will explore several key topics in how an expansion planning model is formulated. First, I will extend co-optimization to different sectors and show how we can co-optimize not only just for generation/transmission, but for entire energy and transportation infrastructure systems. Second, I will talk about the multiple time periods that are modeled within an expansion planning model. Third, I will talk about how uncertainty is modeled in expansion planning. Fourth, I will talk about “anticipatory planning,” which is an iterative, transmission <–> generation expansion planning process that is used in combination with co-optimized expansion planning to help predict how transmission investments will impact generation investments. Fifth, I will talk about “end effects” and some other biases inherent in the transmission planning problem and how these are mitigated. And finally, I will conclude with a brief summary of the material in this blog and the previous two blogs that emphasizes the key concepts of optimization and expansion planning.

Once again, here is a link to Krishnan’s paper: https://link.springer.com/article/10.1007/s12667-015-0158-4


Co-optimization for Different Sectors

Natural Gas

In addition to co-optimizing different resources (like transmission and generation) within the same sector, co-optimization can be extended to optimize investments within different sectors. For example, the paper by Krishnan gave an example of finding optimal siting for a natural gas generator based on the distance of the generator between the natural gas supply region and the load. In other words, it considered the cost of gas pipeline and electricity transmission investments and found the least-cost combination of the two. When working with multiple resources within a network, the optimal build of transmission vs. gas pipeline will also be determined by the network topology – for example, building transmission may be more expensive than a gas pipeline, but it would also benefit other facilities that are not natural gas.

Credit: Krishnan et. al (2015)

Planners also need to consider the geographical coverage of their planning network and what voltage level they wish to model voltages down to. The more nodes and transmission lines are included in a network, the larger and more computationally intensive the model will be. The planning engineer must also consider the tradeoffs they are willing to make with the different levels of model fidelity discussed in the previous blog (transshipment vs. DCOPF vs. ACOPF). Just like the flow of electricity can be modeled at different levels, the flow of natural gas can be as well, with options ranging from a similar transshipment formula that only respects the gas line capacity limits and pipeline flow limits to a more complex model that considers pipeline compressors and flow-pressure relationships.

Batteries and Demand Response

Batteries are becoming an increasingly significant portion of the power system due to their rapidly-decreasing cost. Unlike wind or solar – whose energy output is wholly dependent on meteorological conditions, batteries can dispatch energy on demand. A very profitable strategy for batteries is to have them charge during the middle of the day when solar is plentiful and demand/prices are low, and then discharge during the evening load peak when solar output goes away and prices rise. The addition of batteries into the energy mix has substantially increased power system resilience during extreme summer heat waves, as these batteries can now dispatch several GW of electricity during the evening when it is most needed.

Retrieved from renewableenergyworld.com

That said, batteries are computationally expensive to model in expansion planning optimization tools because one needs to be able to accurately model how they charge and discharge. In the previous two blogs, we’ve talked about the objective function and constraints – where the objective function is minimizing the combined cost of operations and investments, while constraints are technical, economic, and policy constraints that any investment or operational decisions must adhere to.

Krishnan states two important decisions for considerations for any type of storage in an expansion planning model: (1) inter-temporal constraints/simultaneous multi-period optimization, and (2) considering time steps. For (1), the basic storage constraint for an expansion planning model is that the stored energy at period t must equal the energy stored up until period t-1, less any leakage and plus (less) the energy to be charged (discharged) at period t.

For (2) – the time steps over which the constraint in (1) is optimized needs to be consistent with the technology. For example, charge/discharge cycles for short-term battery storage occur within a single day, while the charge/discharge cycles for long-term storage (pumped hydro storage, flow batteries, etc.) can be on the cycle of weeks or even months. For a modeler, the choice of time steps must be balanced with other considerations, such as the fidelity of the power flows, the voltage level of the power lines, the geographic expanse of the planning area, the number of investment periods, and many more.

Time Intervals and Planning Frameworks

The bus example that I gave in the first slide optimizes everything within a single time period. However, many power systems problems need to be optimized over multiple time periods. One example of why this is needed is how thermal generation units are scheduled in the day-ahead market. Thermal units have start-up and shut-down costs, and even if they are not profitable for a given hour, it may be cheaper over the course of the day to keep them online during that hour if it is more economic to keep them running than to incur the startup and shutdown costs. An example of this is with large nuclear plants; it is very expensive to start them up and shut them down, so even if wholesale electricity prices plummet due to a sudden burst of wind and solar, it is cheaper overall to run the unit at a loss during those hours than to incur the startup and shutdown costs.

An expansion planning model needs to consider three separate time periods: (1) the “operational time steps” (interval at which operations within the power sector are modeled), (2) the “optimization period” (interval over which the operations are optimized, and investment decisions are made) and (3) the “planning horizon” (period over which the planning program is executed to identify investments). Unlike real-time markets, where optimization and operations both occur on subhourly time frames, long-term planning involves planning for multiple decades at a time. Planning models need to be able to properly capture the hourly timescales at which thermal plants operate at while making investment decisions at yearly intervals, and they may want to further optimize those investment decisions over the entire planning horizon, not just each sequential investment year.

Krishnan’s paper presents three frameworks for optimizing when dealing with these different timeframes. One is a static optimization, which is when operational time steps, optimization period, and planning horizon are all the same length. The school bus planning problem given in part 1 of this series is an example of a static optimization problem. However, static optimization does not make sense for a planning problem, as it states that operations (like ramping up a natural gas plant) take place on a multi-decadal time scale! The others are multi-period simultaneous optimization, where all optimization periods for the entire planning horizon are considered simultaneously, and multi-period rolling optimization, where the results from one optimization period are sequentially fed into the next. Multi-period simultaneous optimization can make more efficient long-term investments than rolling optimization but at added computational expense.

Anticipatory Planning

In the utility industry, generation & transmission investments are often undertaken by separate entities. “Anticipatory transmission planning” – want to anticipate what, where, and how much generation will be built in response to transmission investment. It is an iterative process that involves (1) creating an initial transmission optimization, (2) feeding this transmission plan as boundary conditions into generation optimization, and (3) feeding the plan given by (2) back into the transmission optimization, continuing to iterate between generation and transmission operation until the solutions converge. While the solutions from the generation & transmission optimization models do not always converge – the occurrences when they do increase confidence in how generation will respond to transmission investment and vise-versa, particularly when the solutions from this iterative process align with a co-optimized approach. Anticipatory transmission planning is often using by Independent System Operators, who are responsible for operating the electrical grid, administering and operating deregulated energy markets, and long-term transmission planning over their domains.

Managing Uncertainty

There are many assumptions we need to make in power system planning models. We certainly don’t want to optimize for a given set of assumptions regarding fuel prices, carbon policies, climate pathways, etc. and then have something else entirely come true. To manage this, Iowa State uses something called “Adaptive Coordinated Expansion Planning” (ACEP). The goal of ACEP is to create a group of “core” investments common to all possible power system “futures” and minimize the cost of “adapting” to any “future,” where a “future” is an economic, political, and environmental trajectory along which society develops. This way, if it becomes clear that things are developing along a certain “future” within ACEP, we will have already made the core investments needed for that plan, and we can easily “steer” the investment plan to reflect that future.

If you are interested in learning more about ACEP, my advisor (Dr. Jim McCalley) did an excellent presentation for the Midcontinent Independent System Operator (MISO) in late 2023. A link to his presentation is here.

Conclusion:

To conclude, co-optimization yields lower costs than decoupled planning. Models of varying fidelity are available, and the choice of model depends on the needs of the planning engineer. Models with higher fidelity, such as ACOPF, are better for detailed transmission planning studies by utilities and ISOs, but they must be run over a smaller geographic area to be computationally tractable. Meanwhile, models with lower fidelity over a larger geographic area are more useful for policy analysis. Co-optimization can extend to different sectors (like fuel & transportation), and planning models include multiple time intervals to capture operations, optimization periods and planning horizon. Anticipatory planning, a decoupled transmission-to-generartion iterative planning process can be used to see how transmission investments will impact generation investment and can increase confidence in the solutions given by co-optimized expansion planning if the two approaches show similar investments. And finally, optimization models can account for uncertainty by creating a set of “core” investments common to multiple power system futures and minimizing the cost of additional investments that “adapt” to any specific future.

That’s all I have for this blog, I hope you enjoyed this series of posts. I’m now finished with my first year at Iowa State and will briefly head back to Seattle to visit family before spending the summer!